Week #10 - Spooky Week
By: Aidan & Morgan
Electrical wiring was continued, we put circular boxes in the ceiling for overhead lights and smoke/monoxide alarms.
The studio kitchen and bathroom sink plumbing were completed early this week. Both are vented and plumbed out of the studio in the bathroom, which will connect to the shower and toilet plumbing underneath the building. This plumbing will be added at a later point.
The cabinetry designs were finalized at the beginning of this week. On Wednesday we started cutting sheets for three of the cabinets. And by the end of the day on Thursday two had been glued together, just waiting on screws. Next week we'll glue the fridge cabinet together and take the two we glued out of clamps.